City of San Diego, a city agency, holds this storm drain permit.

Municipal storm drains

This Phase I municipal storm drain permit has been in place since June 2013.

It covers the storm drains that carry runoff from streets to creeks and the ocean. The Water Board recorded 15 violations and took 67 enforcement actions, 3 of which required a penalty.

Clean WaterMunicipal storm drains

Results only in annual reports

Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.

Permit
Phase I municipal storm drain permit
Permit order
R9-2013-0001
Permit holder
City/Town Agency
Status in the state system
Active
Covered since
June 2013
Area covered
The city's areaA storm drain permit covers an area, so this page has no single map location.
State permit ID
9 37M1000318

Under these permits, the city or agency must keep improving its program to reduce pollution and report on it each year. Test results in local creeks are handled through that process, so we do not judge the permit by them. The yearly reports are not published as data we can read yet.

Violations the Water Board recorded

Listed as the Water Board recorded them.

DateTypeWhat the Water Board recorded
Jan 31, 2022MS4 Order ConditionClass BThe San Diego Bay Bacteria TMDL Responsible Copermittees (Responsible Copermittees) include the cities of San Diego, Lemon Grove, and La Mesa. The Responsible Copermittees failed to properly calculate the wet weather 30-day geometric mean exceedance frequencies for fecal coliform and Enterococcus at stations SD8(1) and ZST in accordance with the requirements of Specific Provision 6.d.(2)(c)(iii)[e] in Attachment E to the Order as part of the 2020-2021 WQIP Annual Report. The Responsible Copermittees also failed to report the wet weather 30-day geometric mean exceedance frequencies for fecal coliform and Enterococcus at station CTL(1) in accordance with the requirements of Specific Provision 6.d.(2)(c)(iii)[e] in Attachment E to the Order as part of the 2020-2021 WQIP Annual Report.
Jan 31, 2022MS4 Order ConditionClass BThe San Diego Bay Bacteria TMDL Responsible Copermittees (Responsible Copermittees) include the cities of San Diego, Lemon Grove, and La Mesa. The Responsible Copermittees failed to properly calculate the dry weather 30-day geometric mean exceedance frequencies for fecal coliform and Enterococcus at station SD8(1), ZST and CTL(1) in accordance with Specific Provision 6.d.(2)(c)(ii)[d] of Attachment E to the Order as part of the 2020-2021 WQIP Annual Report.
Jan 31, 2022MS4 Order ConditionClass BThe San Diego Bay Bacteria TMDL Responsible Copermittees (Responsible Copermittees) include the cities of San Diego, Lemon Grove, and La Mesa. The Responsible Copermittees failed to properly calculate the dry weather single sample maximum exceedance frequencies for fecal coliform and Enterococcus at station SD8(1), ZST, and CTL(1) in accordance with Specific Provision 6.d.(2)(c)(i) of Attachment E to the Order as part of the 2020-2021 WQIP Annual Report.
Jan 31, 2022MS4 Order ConditionClass BThe San Diego Bay Bacteria TMDL Responsible Copermittees (Responsible Copermittees) include the cities of San Diego, Lemon Grove, and La Mesa. Failure to assess 2020-2021 dry and wet weather monitoring data for the Bacteria TMDL at station CTL(1). The Responsible Copermittees did not perform a comparison of collected dry weather and wet weather monitoring data to receiving water limitations for the Chollas Creek mouth monitoring station CTL(1) as part of the 2020-2021 WQIP Annual Report. San Diego Water Board staff reviewed the dry and wet weather monitoring data for the Bacteria TMDL in the 2020-2021 WQIP Annual Report. The report did not include an assessment of the receiving water monitoring data at CTL(1) to assess whether the interim and final receiving water WQBELs for the Chollas Creek segment listed in Table 6.0 have been achieved. Under paragraph 3.a of the 2020-2021 WQIP Annual Report comment letter and via a meeting on March 30, 2022, and April 1, 2022 email, San Diego Water Board staff communicated to the Responsible Copermittees that their approach is inconsistent with the requirements in Specific Provision 6.d.(2) of Attachment E of the Order and the Basin Plan.
Jan 31, 2022MS4 Order ConditionClass BThe City of San Diego failed to properly calculate the dry weather single sample maximum exceedance frequencies for fecal coliform and Enterococcus at station TC-MLS and station TC-TCNP in accordance with Specific Provision 6.d.(2)(c)(i) of Attachment E to the Order as part of the 2020-2021 WQIP Annual Report.
Jan 31, 2022MS4 Order ConditionClass BThe City of San Diego failed to properly calculate the dry weather 30-day geometric mean exceedance frequencies for fecal coliform and Enterococcus at station TC-MLS and station TC-TCNP in accordance with Provision 6.d.(2)(c)(ii)[c] of Attachment E to the Order as part of the 2020-2021 WQIP Annual Report.
Jan 31, 2022MS4 Order ConditionClass BThe City of San Diego failed to properly calculate the wet weather 30-day geometric mean exceedance frequencies for fecal coliform and Enterococcus at station TC-MLS and station TC-TCNP in accordance with the requirements in Specific Provision 6.d.(2)(c)(iii)[e] of Attachment E to the Order as part of the 2020-2021 WQIP Annual Report.
Jan 31, 2022MS4 Order ConditionClass BThe City of San Diego failed to report wet weather 30-day geometric mean exceedance frequencies for total coliform, fecal coliform, and Enterococcus at stations EH-310, EH-320, EH-305, EH-330, EH-340, and FM-080 in accordance with the requirements in Specific Provision 6.d.(1)(c)(iii)[e] of Attachment E to the Order as part of the 2020-2021 WQIP Annual Report.
Jan 31, 2022MS4 Order ConditionClass B
Jan 31, 2022MS4 Order ConditionClass BThe San Dieguito River Bacteria TMDL Responsible Copermittees (Responsible Copermittees) include the County of San Diego and the cities of Del Mar, Escondido, Poway, San Diego, and Solana Beach. The Responsible Copermittees failed to report the wet weather 30-day geometric mean exceedance frequencies for total coliform, fecal coliform, and Enterococcus at station EH-380 in accordance with the requirements in Specific Provision 6.d.(1)(c)(iii)[e] of Attachment E to the Order as part of the 2020-2021 WQIP Annual Report.
Jan 20, 2022Unauthorized NSWDClass BInvestigation of unauthorized non-stormwater discharge from power washing during emergency drought throughout Hillcrest Business Association. first violation reported 1/20/2022. Power washing occurring on monthly basis.
Feb 18, 2018Deficient ReportClass 3Review of the Regional Clearinghouse, with respect to GIS data, layers, and/or shapefiles, the San Diego Water Board concludes that the Copermittee is non-compliant with provision F.4 of the Regional MS4 Permit.
Dec 15, 2017Deficient BMP ImplementationClass BPursuant to provision E.4.a (4) of the Order, the City failed to implement its Construction Management Program: The City failed to confirm, prior to issuance of any local permit(s) that allows the commencement of construction projects that involve ground disturbance or soil disturbing activities that can potentially generate pollutants in storm water runoff, that the project applicant has obtained coverage under the statewide Construction General Permit (Order 2009-0009-DWQ or subsequent Order)
Dec 15, 2017Deficient BMP ImplementationClass BPursuant to provision E.1.a (9) of the Order, the City failed to utilize enforcement mechanisms to require compliance with its statutes, ordinances, permits, contracts, orders, or similar means for the MCCP-3Roots project.
Dec 15, 2017Deficient BMP ImplementationClass BPursuant to provision E.1.a (6) of the Order, the City failed to require compliance with conditions in its statutes, ordinances, permits, contracts, orders, or similar means to hold dischargers to its MS4 accountable for their contributions of pollutants and flows for the MCCP-3Roots project

Enforcement actions

Notices, orders, and penalties the Water Board issued.

DateActionDetailsPenalty
Feb 18, 2025Notice of violationThe California Regional Water Quality Control Board, San Diego Region (San DiegoWater Board) is issuing this Notice of Violation R9-2025-0049 to the City of San Diego(City) for failure to comply with National Pollutant Discharge Elimination System(NPDES) Permit No. CAS0109266 and Waste Discharge Requirements for Dischargesfrom the Municipal Separate Storm Sewer Systems (MS4s) Draining the WatershedsWithin the San Diego Region, Order No. R9-2013-0001, as amended (Order). Failure to monitor pursuant to Order Provision II.D.2.b.(2)(e)(iii)[b] and II.D.2.c.(5)(f)(ii)Status: Historical
Mar 13, 2024Time schedule orderOrder R9-2024-0010The California Regional Water Quality Control Board, San Diego Region (San Diego Water Board) adopted Time Schedule Order No. R9-2024-0010, An Order Requiring Designated Responsible Permittees to Comply with Bacteria, Project I-Twenty Beaches and Creeks TMDL Requirements Prescribed in the Regional Municipal Separate Storm Sewer Systems Permit for the San Diego Region (TSO No. R9-2024-0010) at its meeting on Wednesday, March 13, 2024. The City of San Diego is listed as a TSO Responsible Permittee and must comply with the requirements prescribed in TSO No. R9-2024-0010.Status: Active
Dec 15, 2023Notice of violationOrder R9-2023-0197The California Regional Water Quality Control Board, San Diego Region (San Diego Water Board) is issuing Notice of Violation (NOV) No. R9-2023-0197 to the Bacteria TMDL Responsible Copermittees in the San Diego Bay Watershed Management Area for failure to comply with National Pollutant Discharge Elimination System (NPDES) Permit No. CAS0109266 and Waste Discharge Requirements for Discharges from the Municipal Separate Storm Sewer Systems (MS4s) Draining the Watersheds Within the San Diego Region, Order No. R9-2013-0001. The San Diego Bay Bacteria TMDL Responsible Copermittees include the cities of San Diego, Lemon Grove, and La Mesa.Status: Historical
Dec 15, 2023Notice of violationOrder R9-2023-0200The California Regional Water Quality Control Board, San Diego Region (San Diego Water Board) is issuing Notice of Violation (NOV) No. R9-2023-0200 to the Bacteria TMDL Responsible Copermittees in the Mission Bay Watershed Management Area for failure to comply with National Pollutant Discharge Elimination System (NPDES) Permit No. CAS0109266 and Waste Discharge Requirements for Discharges from the Municipal Separate Storm Sewer Systems (MS4s) Draining the Watersheds Within the San Diego Region, Order No. R9-2013-0001. The Mission Bay Bacteria TMDL Responsible Copermittee is the City of San Diego.Status: Historical
Dec 15, 2023Notice of violationOrder R9-2023-0201Status: Historical
Dec 15, 2023Notice of violationOrder R9-2023-0198The California Regional Water Quality Control Board, San Diego Region (San Diego Water Board) is issuing Notice of Violation (NOV) No. R9-2023-0198 to the Bacteria TMDL Responsible Copermittees in the San Dieguito River Watershed Management Area for failure to comply with National Pollutant Discharge Elimination System (NPDES) Permit No. CAS0109266 and Waste Discharge Requirements for Discharges from the Municipal Separate Storm Sewer Systems (MS4s) Draining the Watersheds Within the San Diego Region, Order No. R9-2013-0001. The San Dieguito River Bacteria TMDL Responsible Copermittees include the County of San Diego and the cities of Del Mar, Escondido, Poway, San Diego, and Solana Beach.Status: Historical
Jul 21, 2022Order to submit informationOrder R9-2022-0128Investigative Order R9-2022--128Status: Active
Feb 6, 2020Notice of violationNOV R9 2020-0025: Failure to comply with Order No. R9-2013-0001, as amended by Order Nos. R9-2015-0001 and R9-2015-0100 NPDES No. CAS0109266 Permit and Waste Discharge Requirements for Discharges from the Municipal Separate Storm Sewer Systems Draining the Watersheds Within the San Diego Region: Provision E.1.a (6) of the Order, the City failed to require compliance with conditions in its statutes, ordinances, permits, contracts, orders, or similar means to hold dischargers to its MS4 accountable for their contributions of pollutants and flows;Status: Historical
Feb 6, 2020Notice of violationNOV R9 2020-0025 Failure to comply with Order No. R9-2013-0001, as amended by Order Nos. R9-2015-0001 and R9-2015-0100 NPDES No. CAS0109266 Permit and Waste Discharge Requirements for Discharges from the Municipal Separate Storm Sewer Systems Draining the Watersheds Within the San Diego Region. Provision E.1.a (9) of the Order - the City failed to utilize enforcement mechanisms to require compliance with its statutes, ordinances, permits, contracts, orders, or similar means for the MCCP-3Roots project.Status: Historical
Feb 6, 2020Notice of violationNOV R9 2020-0025:Failure to comply with Order No. R9-2013-0001, as amended by Order Nos. R9-2015-0001 and R9-2015-0100 NPDES No. CAS0109266 Permit and Waste Discharge Requirements for Discharges from the Municipal Separate Storm Sewer Systems Draining the Watersheds Within the San Diego Region. Provision E.4.a (4) of the Order, the City failed to implement its Construction Management Program. The City failed to confirm, prior to issuance of any local permit(s) that allows the commencement of construction projects that involve ground disturbance or soil disturbing activities that can potentially generate pollutants in storm water runoff, that the project applicant has obtained coverage under the statewide Construction General Permit (Order 2009-0009-DWQ or subsequent Order) for the MCCP-3Roots project.Status: Historical
Aug 9, 2017Penalty orderOrder R9-2017-0056ACLC for failure to implement effective construction oversight program that resulted in the discharges of sediment that was not reduced to the MEP. Close out letter sent 8/27/20Status: HistoricalPenalty required
Feb 20, 2015Notice of violationOrder R9-2015-0031Notice of Violation No. R9-2015-0031 for City Stormwater Construction Management ProgramStatus: Historical
Aug 13, 2014Time schedule orderOrder R9-2014-0034Time schedule order adopted at the August 13, 2014 San Diego Water Board meeting. The CIty must bring 150 non compliant sites into compliance with Municipal Storm water post construction BMP requirements by August 15, 2016Status: Historical
Aug 13, 2014Penalty orderOrder R9-2014-0017Stipulated Settlement Order R9-2014-0017 for violations of MS4 Permit R9-2007-0001Status: HistoricalPenalty required
Mar 7, 2014Notice of violationOrder R9-2014-0024NOV issued to City of SD for failure to require implementation of minimum BMPs at construction sites.Status: Historical
Jan 26, 2011Notice of violationOrder R9-2011-0027Failure to enforce construction oversight provisions of municipal permit, Order No. R9-2007-0001Status: Historical
Oct 1, 2010Notice of violationOrder R9-2010-0135NOV/13267 request for technical report to the City of San Diego for SUSMP violation of MS4 permitsStatus: Historical
Feb 1, 2010Notice of violationOrder R9-2010-0015Failure to require minimum BMPs at Quarry Falls, failure to inspect construction site, failure to keep pollutants out of MS4 to the MEPStatus: Historical
Jul 26, 2007Order to submit informationOrder R9-2007-011013267 letter request for technical report due to violations of the MS4 permit.Status: Historical
Dec 22, 2006Notice of violationOrder R9-2006-0164Failure to eliminate illicit dischargesStatus: Historical
Dec 22, 2006Order to submit informationOrder R9-2006-0164Failure to submit information, Sept. 15, 2006 CWCStatus: Historical
Sep 15, 2006Notice of violationOrder R9-2006-00461. Failure to Conduct Follow-up Investigations (V ID# 470136) 2. Failure to Prioritize Industrial Sites ( V ID # 470138)Status: Historical
Sep 15, 2006Order to submit informationOrder R9-2006-0046Failure to conduct follow-up investigations. Failure to classify industrial sites as high, medium, or low threat to water quality.Status: Historical
Sep 11, 2006Order to submit informationOrder UNKNOWNLetter requesting information on follow up on dry weather screening and analytical monitoring resultsStatus: Historical
Sep 11, 2006Notice of violationOrder R9-2006-0115Failure to conduct follow-up investigations as required by section F.5.C Regional Board Order No. 2001-01.Status: Historical
May 6, 2005Notice of violationOrder R9-2005-0125Failure to conduct required follow up investigations of dry weather field screening results.Status: Historical
May 6, 2005Order to submit informationOrder R9-2005-0125Failure to conduct required follow-up investigations of dry weather field screening resultsStatus: Historical
Apr 5, 2005Order to submit informationOrder UNKNOWNA 13267 letter to investigate the City's compliance with the Municipal Storm Water Permit at the Carmel Valley Trunk Sewer construction project.Status: Historical
Mar 23, 2005Order to submit informationOrder UNKNOWN13267 requesting information for failure to reduce the discharge of pollutants from eroding dirt alley to the maximum extent practicable.Status: Historical
Mar 23, 2005Notice of violationOrder UNKNOWNNOV for failure to reduce discharge of pollutants from eroding dirt alley to the maximum extent practicable.Status: Historical
Mar 16, 2005Notice of violationOrder R9-2005-0104Failed to ensure the implementation of BMPs for erosion and sediment control to the MEPStatus: Historical
Mar 10, 2005Order to submit informationOrder UNKNOWN13267 requesting information on BMP implementation and permit coverage.Status: Historical
Mar 10, 2005Notice of violationOrder UNKNOWNNOV for failure to implement adequate storm water BMPs at a City construction site.Status: Historical
Mar 8, 2005Order to submit informationOrder UNKNOWN13267 for information on how complaints of illicit discharges are handled.Status: Historical
Mar 8, 2005Notice of violationOrder UNKNOWNNOV for failure to eliminate illicit discharge of used motor oil after being notified of illicit discharge.Status: Historical
Feb 23, 2005Verbal warningOrder UNKNOWNNotified City of San Diego that adequate storm water BMPs needed to be required and implemented at the construction site at the corner of Jenkins and San Elijo Streets in Point Loma, San Diego.Status: Historical
Feb 10, 2005Verbal warningOrder UNKNOWNNotified City of continuing sediment discharges at 2994-3010 Reynard Way and need to increase enforcement.Status: Historical
Jan 10, 2005Order to submit informationOrder UNKNOWN13267 letter requesting information on BMP implementation and permit coverage at City of San Diego La Jolla Village Drive Widening construction site.Status: Historical
Jan 10, 2005Notice of violationOrder UNKNOWNFailure to implement adequate storm water BMPs at a City construction site (La Jolla Village Drive Widening).Status: Historical
Dec 10, 2004Order to submit informationOrder UNKNOWN13267 requesting information on corrective actions and permit coverage.Status: Historical
Dec 10, 2004Notice of violationOrder UNKNOWNNOV for failure to adequately implement storm water BMPs at municipal construction site.Status: Historical
Apr 20, 2004Order to submit informationOrder UNKNOWN13267 letter for dredging without a permit in Tijuana River Valley. Report due May 20, 2004.Status: Historical
Apr 20, 2004Notice of violationOrder R9-2004-0099NOV for dredging without a permit in Tijuana River Valley.Status: Historical
Apr 20, 2004Staff enforcement letterOrder UNKNOWNInspection Report for lack of BMPs at spoils storage area and dredging without a permit in the Tijuana River Valley.Status: Historical
Apr 12, 2004Notice of violationOrder R9-2004-0110Failure to capture wash water from power washing resulted in discharge to MS4Status: Historical
Apr 7, 2004Order to submit informationOrder R9-2004-011013267 requesting info. on City's power washing programStatus: Historical
Mar 25, 2004Order to submit informationOrder UNKNOWNNOV for failure to implement adequate BMPs in canyons where sewer work is occurring and 13267 letter requesting information on corrective actions taken.Status: Historical
Nov 6, 2003Order to submit informationOrder UNKNOWN13267 requesting information to ensure that high priority industrial facilities are inspected annually.Status: Historical
Oct 30, 2003Order to submit informationOrder UNKNOWNNOV for failure to implementat adequate BMPs at municipal yard and 13267 requesting information on how inadequate BMPs at municipal yard were correctedStatus: Historical
Apr 15, 2003Verbal warningOrder UNKNOWNVerbally notified City of San Diego regarding additional BMPs and BMP maintenance being needed in the Arroyo Sorrento Road areaStatus: Historical
Mar 14, 2003Verbal warningOrder UNKNOWNAfter observing inadequate BMPs a water line break location, I called Tony Evans at the City of San Diego to notify him and ask him to correct the BMPs. He stated he would correct the problem.Status: Historical
Mar 4, 2003Order to submit informationOrder UNKNOWNNotice of Violation and 13267 Required Technical ReportStatus: Historical
Jan 27, 2003Order to submit informationOrder UNKNOWNRequired the City of San Diego submit a Technical report because the Casitas construction site failed to implement BMP for sediment control. We issued NOV and 13267 letter to Casitas on 1/27/03. The SWIM number for the Violation is 135773, NOV is 68567Status: Historical
Dec 18, 2002Order to submit informationOrder UNKNOWN13267 requiring another iteration of BMP implementation to address the continued exceedances ofwater quality standards for trash/floating material in Chollas and Paleta CreeksStatus: Historical
Dec 10, 2002Order to submit informationOrder UNKNOWNNotice of Violation for failure to ensure implementation of BMPs at small construction site and 13267 requesting BMP information regarding BMPs at small construciton site.Status: Historical
Nov 27, 2002Staff enforcement letterOrder UNKNOWNWrote informal email requiring implementation of adequate BMPs at water/sewer line relacement jobStatus: Historical
Nov 26, 2002Order to submit informationOrder UNKNOWNNotice of Violation and 13267 Required Technical ReportStatus: Historical
Jul 30, 2002Verbal warningOrder UNKNOWNPut City of San Diego on notice for active preparation and implementation of construction BMPs per JURMP for all applicable private sites in advance of the rainy season.Status: Historical
Jun 25, 2002Verbal warningOrder UNKNOWNStacey Baczkowski notified City of San Diego verbally and via email on 6/25/02Status: Historical
Jun 21, 2002Verbal warningOrder UNKNOWNNon-implementation of construction BMPs per JURMPStatus: Historical
Nov 7, 2001Order to submit informationOrder UNKNOWNThe City and the Port District were requested to investigate PCBs in the storm drains tributary to Convair Lagoon. Workplan is due by 1/4/02Status: Historical
Aug 30, 2000Penalty orderOrder R9-2000-0121CAO No. 98-50 Directive 1.c. 365 days of violation at $800/day. Directive 2. 294 days of violation at $800/day. Directive 2. days of violation was reduced from 300 alleged in complaint due to the submittal of a Long-Term BMP plan on 3 August 2000.Status: HistoricalPenalty required
Jul 3, 2000Order to submit informationOrder UNKNOWNRequested the following info: 1 Res. Eng. inspection rpts/logs for ColRich, including sw viols & followup; 2 ColRich grading permit; 3 ColRich proj plan 4 Allowance of ColRich's rainy season grading 5 Mtg notes w/ColRich 6 Council ColRich resolutionStatus: Historical
Apr 20, 2000Order to submit informationOrder UNKNOWNRequest for information regarding the ColRich construction site on Arroyo Sorrento Road.Status: Historical
Apr 19, 2000Notice of violationOrder UNKNOWNNOV No. 2000-88. Failure to implement BMPs and to prohibit illicit/illegal discharges as required by Order No. 90-42 in regards to discharge of sediment from ColRich development on Arroyo Sorrento Road.Status: Historical
Feb 2, 2000Notice of violationNOV No. 2000-26 for City's failure to comply with CAO No. 98-50 directives 1.c. (implement short-term BMPs by 15 Oct 1998) & 2. (develop & implement long-term BMPs by 15 Oct 1999.).Status: Historical
Dec 21, 1999Staff enforcement letterOrder UNKNOWNFailure to pay annual fee.Status: Historical

Source: the State Water Board's stormwater system (SMARTS).

Location and details

Permits and IDs

Operator
City of San Diego
Covered by
Municipal storm drain permit

The state stormwater record

Report pollution at this site