Cutting Edge Supply Co has held an industrial stormwater permit for the site since September 2007. Its industry is listed as construction machinery and equipment. Every pollutant it tested in 2025-26 averaged within the state benchmarks.

234 East O St, Colton

Industrial stormwater

During the 2025-2026 rainy season, every pollutant this site tested in its runoff averaged within the state's benchmarks.

That is based on 6 lab results from 2 storm days.

Clean WaterIndustrial stormwater

Within the state benchmarks

Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.

Rain and sampling in 2025-26

The facility sampled 2 of the 12 storms of a tenth of an inch or more near the site in 2025-26.

The permit generally requires samples from four storms a year, with few exceptions. The facility told the state it missed storms because not enough qualifying storms occurred, storms did not produce a discharge, and storms fell outside operating hours.

What the samples show

The state compares each year's average with its benchmark. A site with more than one drainage area samples each one separately, so it can file more than four results for a pollutant in a year. Open a pollutant to see every lab result behind the averages.

  • Yearly average, over
  • Yearly average, within
  • Single lab result
  • State benchmark

Tested in 2025-26

pH

6.9 to 7.22 results

6 to 9

All results for pH

Water that is too acidic or too alkaline harms aquatic life and makes metals more toxic.

24 results as a table
SampledDrainage areaResult
Oct 22, 2026Driveway6.4
Feb 16, 2026Driveway6.9
Dec 30, 2025Driveway7.2
Mar 13, 2025Driveway6.9
Feb 13, 2025Driveway7.2
Jan 3, 2024Driveway9
Feb 23, 2023Driveway8
Nov 8, 2022Driveway7.8
Dec 9, 2021Driveway7
Oct 25, 2021Driveway8
Mar 15, 2021Driveway7
Jan 29, 2021Driveway8
Dec 28, 2020Driveway7
Apr 6, 2020Driveway7
Dec 4, 2019Driveway7
May 10, 2019Driveway8
Jan 31, 2019Driveway7
Jan 14, 2019Driveway7
Mar 22, 2018Driveway7
Jan 8, 2018Driveway7
Feb 28, 2017Driveway7
Feb 6, 2017Driveway7
Dec 16, 2016Driveway6.6
Sep 15, 2015Driveway7

Suspended solids

28 mg/L2 results

100 mg/L

All results for suspended solids

Mud and fine particles that cloud water, bury habitat, and carry other pollutants.

24 results as a table
SampledDrainage areaResult
Oct 22, 2026Driveway74 mg/L
Feb 16, 2026Driveway39 mg/L
Dec 30, 2025Driveway17 mg/L
Mar 13, 2025Driveway13 mg/L
Feb 13, 2025Driveway45 mg/L
Jan 3, 2024Driveway26 mg/L
Feb 23, 2023Driveway75 mg/L
Nov 8, 2022Driveway91 mg/L
Dec 9, 2021Driveway15 mg/L
Oct 25, 2021Driveway67 mg/L
Mar 15, 2021Driveway114 mg/L
Jan 29, 2021Driveway17 mg/L
Dec 28, 2020Driveway24 mg/L
Apr 6, 2020Driveway100 mg/L
Dec 4, 2019Driveway25 mg/L
May 10, 2019Driveway43 mg/L
Jan 31, 2019Driveway35 mg/L
Jan 14, 2019Driveway12 mg/L
Mar 22, 2018Driveway34 mg/L
Jan 8, 2018Driveway91 mg/L
Feb 28, 2017Driveway60 mg/L
Feb 6, 2017Driveway17 mg/L
Dec 16, 2016Driveway16 mg/L
Sep 15, 2015Driveway26 mg/L

Oil and grease

Not detected2 results

15 mg/L

All results for oil and grease

Coats plants and animals and blocks oxygen from entering the water.

24 results as a table
SampledDrainage areaResult
Oct 22, 2026DrivewayNot detected
Feb 16, 2026DrivewayNot detected
Dec 30, 2025DrivewayNot detected
Mar 13, 2025DrivewayNot detected
Feb 13, 2025Driveway3.6 mg/L
Jan 3, 2024DrivewayNot detected
Feb 23, 2023DrivewayNot detected
Nov 8, 2022DrivewayNot detected
Dec 9, 2021DrivewayNot detected
Oct 25, 2021DrivewayNot detected
Mar 15, 2021DrivewayNot detected
Jan 29, 2021DrivewayNot detected
Dec 28, 2020DrivewayNot detected
Apr 6, 2020Driveway4.5 mg/L
Dec 4, 2019Driveway1 mg/L
May 10, 2019Driveway2.4 mg/L
Jan 31, 2019Driveway2.2 mg/L
Jan 14, 2019Driveway1.3 mg/L
Mar 22, 2018Driveway0.9 mg/L
Jan 8, 2018Driveway2.1 mg/L
Feb 28, 2017Driveway2.8 mg/L
Feb 6, 2017Driveway1.2 mg/L
Dec 16, 2016Driveway0.8 mg/L
Sep 15, 2015DrivewayNot detected

Rain and sampling by year

The permit asks each site to sample two storms between July and December and two between January and June. When a site samples fewer, its results may not represent its true runoff.

  • Day with rain
  • Day sampled
2025-26

2 of 12 storms sampledTold the state: not enough qualifying storms occurred; storms did not produce a discharge; storms fell outside operating hours

2024-25

2 of 8 storms sampledTold the state it did not sample every required storm

2023-24

1 of 18 storms sampledTold the state it did not sample every required storm

2022-23

2 of 16 storms sampledTold the state it did not sample every required storm

2021-22

2 of 11 storms sampledTold the state it did not sample every required storm

2020-21

2 of 7 storms sampledTold the state it did not sample every required storm

Rainfall comes from the daily records of NOAA station Redlands (USC00047306), 7.5 miles from the site. It is the nearest station with a full record since 2015. A storm here means a tenth of an inch or more of rain after two dry days.

Location and details

Where the runoff goes

The facility reports that rain running off it drains to Santa Ana.

Storm drains carry this runoff to creeks and the ocean without treatment.

The neighborhood

About 4,804 people live in the neighborhood around this site in Colton. The state scores it above 94% of California neighborhoods for pollution burden and health vulnerability.

Least burdenedMost burdened

Source: CalEnviroScreen 5.0, census tract 6071012500. The score covers the whole neighborhood and does not measure this site's own effect.

Same operator

Cutting Edge Supply Co holds 1 other stormwater permit:

Permits and IDs

Industry
Construction Machinery and Equipment
Operator
Cutting Edge Supply Co
Covered by
Industrial stormwater permit
Stormwater permit since
September 2007
Site size
7.1 acres
State stormwater ID
8 36I021156

The state stormwater record

Other sites nearby

Report pollution at this site

Send photos or video of what you have seen, such as smoke, runoff, or uncovered materials. We review every report.

Send a report