Construction stormwater
The state says this construction site needs a stormwater permit and has none on file.
It is listed as "NOI Required" in the state's permit system. The Water Board recorded 1 violation and took 1 enforcement action.
7010 Chili Hill Road, Newcastle, CA 95658
Billy Wing operates the site. The state has told it to get a construction stormwater permit.
We could not place this address on the map.
The state says this construction site needs a stormwater permit and has none on file.
It is listed as "NOI Required" in the state's permit system. The Water Board recorded 1 violation and took 1 enforcement action.
Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.
The permit's action levels are a pH between 6.5 and 8.5 and turbidity of 250 NTU, checked at each discharge point for each day of discharge.
At its risk level, the permit does not require samples of discharges, so no results are expected.
Listed as the Water Board recorded them.
| Date | Type | What the Water Board recorded |
|---|---|---|
| May 10, 2019 | Failure to Obtain PermitClass 2 | Failure to obtain IGP coverage. |
Notices, orders, and penalties the Water Board issued.
| Date | Action | Details | Penalty |
|---|---|---|---|
| May 10, 2019 | Notice of non-compliance | Failure to obtain IGP coverage.Status: Active |
Source: the State Water Board's stormwater system (SMARTS). Sites report pH and turbidity readings taken in the field when a storm makes them discharge.