Pulte Home Company LLC operates the site. Its discharge was above the permit's action level on 1 day in the last 12 months.
N of Highway 65 &, Lincoln
Construction stormwater
On 1 day in the last 12 months, a discharge from this construction site was above the permit's action level for turbidity.
The permit's action levels are a pH between 6.5 and 8.5 and turbidity of 250 NTU, checked at each discharge point for each day of discharge. The permit does not count a day above an action level as a violation. The Water Board recorded 1 violation and took 1 enforcement action.
Clean WaterConstruction stormwater
Above the permit's action level
Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.
Permit
Construction stormwater permit
Risk level
Risk level 2The permit requires samples of discharges at this level.
Status in the state system
Active
Covered since
November 2024
Disturbed area
77.24 acres
Project
Residential
State permit ID
5S31C405555
Days above the permit's action level
The permit's action levels are a pH between 6.5 and 8.5 and turbidity of 250 NTU, checked at each discharge point for each day of discharge.
Date
Discharge point
Measure
Day's value
Level
Dec 24, 2025
WW-05
Turbidity
500 NTU
above 250 NTU
Nov 17, 2025
WW-04
Turbidity
705 NTU
above 250 NTU
Nov 17, 2025
WW-05
Turbidity
402 NTU
above 250 NTU
Feb 13, 2025
WW-05
Turbidity
917 NTU
above 250 NTU
All field readings (8)
Date
Discharge point
pH
Turbidity
Apr 21, 2026
WW-05
7.3
78 NTU
Feb 19, 2026
WW-05
7.7
177 NTU
Feb 17, 2026
WW-05
7.8
166 NTU
Dec 24, 2025
WW-05
7.8
500 NTU
Nov 17, 2025
WW-04
7.5
705 NTU
Nov 17, 2025
WW-05
6.9
402 NTU
Feb 13, 2025
WW-05
7.7
917 NTU
Feb 6, 2025
WW-05
6.8
180 NTU
Violations the Water Board recorded
Listed as the Water Board recorded them.
Date
Type
What the Water Board recorded
Aug 28, 2025
Deficient BMP ImplementationClass B
Sediment control BMPs in need of maintenance and the concrete washout was inadequate with evidence of liquid discharge to the underlying soil.
Enforcement actions
Notices, orders, and penalties the Water Board issued.
Date
Action
Details
Penalty
Sep 10, 2025
Verbal warning
Deficiencies communicated in inspection transmittal.Status: Historical
Source: the State Water Board's stormwater system (SMARTS). Sites report pH and turbidity readings taken in the field when a storm makes them discharge.
Location and details
The neighborhood
About 3,361 people live in the neighborhood around this site in Lincoln. The state scores it above 5% of California neighborhoods for pollution burden and health vulnerability.
Least burdenedMost burdened
Source: CalEnviroScreen 5.0, census tract 6061023900. The score covers the whole neighborhood and does not measure this site's own effect.