| Jul 30, 2025 | Administrative Civil LiabilityOrder R5-2025-0517 | Status: Historical | Penalty required |
| Jan 17, 2025 | Notice of Violation | Status: Historical | |
| Aug 23, 2024 | Notice of Violation | Status: Historical | |
| Mar 25, 2024 | Notice of Violation | Status: Historical | |
| Sep 20, 2023 | Notice of Violation | Status: Historical | |
| Apr 25, 2023 | Notice of Violation | Status: Historical | |
| Sep 8, 2022 | Administrative Civil LiabilityOrder R5-2022-0508 | Status: Historical | Penalty required |
| Apr 7, 2022 | Notice of Violation | Status: Historical | |
| Jan 27, 2022 | Administrative Civil LiabilityOrder R5-2021-0531 | Status: Historical | Penalty required |
| Dec 29, 2021 | Notice of Violation | Status: Historical | |
| Jul 26, 2021 | Notice of Violation | Status: Historical | |
| Feb 25, 2021 | Administrative Civil LiabilityOrder R5-2020-0567 | Status: Historical | Penalty required |
| Feb 11, 2021 | Notice of Violation | Status: Historical | |
| Oct 5, 2020 | Notice of Violation | Status: Historical | |
| May 1, 2020 | Notice of Violation | Status: Historical | |
| Mar 27, 2020 | Notice of Violation | Status: Historical | |
| Feb 27, 2020 | Notice of Violation | Status: Historical | |
| Jan 9, 2020 | Administrative Civil LiabilityOrder R5-2019-0535 | This Offer to Participate in the Central Valley Regional Water Quality Control Board's (Central Valley Water Board's) Expedited Payment Letter (EPL) Program (Conditional Offer) provides the Discharger with an opportunity to resolve mandatory minimum penalties for alleged NPDES permit violations without a formal administrative civil liability complaint. The alleged mandatory minimum penalty, in the amount of one hundred twenty-nine thousand dollars ($129,000), represents the sum of accrued man...The Water Board marks this as a mandatory minimum penalty.Status: Historical | Penalty required |
| Sep 9, 2019 | Administrative Civil LiabilityOrder R5-2019-0513 | The Expedited Payment Letter (EPL) Program (Conditional Offer) provides the Discharger with an opportunity to resolve mandatory minimum penalties for effluent violations without a formal administrative civil liability complaint. The alleged mandatory minimum penalty, in the amount of one hundred thirty eight thousand dollars ($138,000), represents the sum of accrued mandatory minimum penalties for effluent limitation violations specifically identified in the Record of Violations (Attachment A...The Water Board marks this as a mandatory minimum penalty.Status: Historical | Penalty required |
| Aug 20, 2019 | Notice of Violation | Status: Historical | |
| Mar 11, 2019 | Notice of Violation | Status: Historical | |
| Jan 4, 2019 | Administrative Civil LiabilityOrder R5-2018-0536 | The Expedited Payment Letter Program (EPL) provides the Discharger with an opportunity to resolve mandatory minimum penalties for effluent violations without a formal administrative civil liability Complaint. The alleged mandatory minimum penalty, in the amount of fifteen thousand dollars ($15,000).The Water Board marks this as a mandatory minimum penalty.Status: Historical | Penalty required |
| Aug 31, 2018 | Notice of Violation | Status: Historical | |
| Jun 19, 2018 | Notice of Violation | Status: Historical | |
| Apr 5, 2018 | Notice of Violation | Status: Historical | |
| Feb 1, 2018 | Time Schedule OrderOrder R5-2017-0120 | This Order provides a time schedule for completing the actions necessary to ensure compliance with the final effluent limitations for temperature contained in WDR Order R5-2017-0119.Status: Active | |
| Dec 8, 2017 | State CWA Non Penalty AO | | |
| Jun 8, 2017 | Notice of Violation | Status: Historical | |
| Apr 3, 2017 | Notice of Violation | Status: Historical | |
| Oct 12, 2016 | Notice of Violation | Status: Historical | |
| Aug 25, 2016 | Notice of Violation | Status: Historical | |
| Oct 9, 2015 | Administrative Civil LiabilityOrder R5-2015-0539 | The Complaint charges the Discharger with administrative civil liability in the amount of $39,000, which represents the sum of accrued Mandatory Minimum Penalties for effluent limitation violations that occurred from 1 January 2009 through 30 June 2015. There are 12 serious violations and 1 non-serious violation subject to MMPs.The Water Board marks this as a mandatory minimum penalty.Status: Historical | Penalty required |
| Jul 2, 2015 | Notice of Violation | Status: Historical | |
| May 30, 2013 | Notice of Violation | During the monitoring periods December 2012, Fourth Quarter 2012, Annual 2012, January 2013, February 2013, March 2013, and First Quarter 2013 the discharge violated the limitations contained in the WDRs.Status: Historical | |
| Feb 8, 2013 | Notice of Violation | During the monitoring periods October 2012 and November 2012 the discharge violated the limitations contained in the WDRs.Status: Historical | |
| Jan 31, 2013 | Time Schedule OrderOrder R5-2013-0005 | 01/31/2018: Rescinded by TSO R5-2017-0120. The NPDES permit renewal includes effluent limitations for temperature that the Facility cannot immediately comply. Therefore, a Time Schedule Order is to allow time schedule for compliance with final temperature limitationsStatus: Historical | |
| Sep 13, 2012 | Notice of Violation | During the monitoring periods April 2012, May 2012, June 2012, July 2012, and Second Quarter 2012 the discharge violated the limitations contained in the WDRs.Status: Historical | |
| Aug 3, 2012 | Time Schedule OrderOrder R5-2012-0073 | TSO issued to replace TSO R5-2009-0013. The discharger requests for additional time to comply with the final effluent limitations for dibromochloromethane and dichlorobromomethaneStatus: Historical | |
| Jun 1, 2012 | Notice of Violation | During the monitoring periods August 2011, September 2011, Third Quarter 2011, October 2011, November 2011, December 2011, Fourth Quarter 2011, Annual 2011, January 2012, February 2012, March 2012, and First Quarter 2012 the discharge violated the limitations contained in the WDRs.Status: Historical | |
| Jul 18, 2011 | Notice of Violation | Status: Historical | |
| May 18, 2011 | Notice of Violation | During the monitoring periods February 2011, and March 2011 the discharge violated the limitations contained in the WDRs.Status: Historical | |
| Mar 22, 2011 | Notice of Violation | During the monitoring period January 2011 the discharge violated the limitations contained in the WDRs.Status: Historical | |
| Feb 11, 2011 | Notice of Violation | December 2010 SMR does not fully comply with the MRP requirements.Status: Historical | |
| Jan 26, 2011 | Notice of Violation | Effluent limitation violations that have occurred at the facility from 1 January 2009 through 30 November 2010.Status: Historical | |
| Jan 26, 2011 | Notice of Violation | During the monitoring periods October 2010 and November 2010 the discharge violated the effluent limitations contained in the WDRs. November 2010 SMR does not fully comply with the MRP requirements.Status: Historical | |
| Dec 7, 2010 | Notice of Violation | During the monitoring period September 2010 the discharge violated the effluent limitations contained in the WDRs. September 2010 SMR does not fully comply with the MRP requirements.Status: Historical | |
| Oct 26, 2010 | Notice of Violation | During the monitoring period August 2010 the discharge violated the effluent violation contained in the WDRs.Status: Historical | |
| Sep 13, 2010 | Notice of Violation | During the monitoring period July 2010 the discharge violated the effluent limitations contained in the WDRs.Status: Historical | |
| Aug 18, 2010 | Notice of Violation | In June 2010 the discharge violated the effluent limitations contained in the WDRs and June 2010 SMR does not fully comply with the MRP requirements.Status: Historical | |
| Jul 20, 2010 | Notice of Violation | In May 2010 the discharge violated the effluent limitations for Bis(2-exhylhexyl)phthalate, Dichlorobromomethane and Chlorodibromomethane contained in the WDRs. May 2010 SMR does not fully comply with the MRP requirements.Status: Historical | |
| Jun 22, 2010 | Notice of Violation | April 2010 SMR does not fully comply with the MRP requirements and the discharge violated the effluent limitations set forht in WDRs Order R5-2007-0039.Status: Historical | |
| May 25, 2010 | Notice of Violation | March 2010 SMR does not fully comply with the MRP requirements and insufficient report cover letter.Status: Historical | |
| Dec 23, 2009 | Notice of Violation | Status: Historical | |
| Mar 16, 2009 | Administrative Civil LiabilityOrder R5-2009-0516 | MMP Complaint issued in the amount of $30,000 for 10 serious effluent limitation violations from 2/1/2008 to 12/31/2008.The Water Board marks this as a mandatory minimum penalty.Status: Historical | Penalty required |
| Feb 5, 2009 | Time Schedule OrderOrder R5-2009-0013 | TSO issued to replace TSO R5-2007-0040. The discharger shall develop, submit, and implement methods of compliance including pollution prevention activities, or construct necessary treatment facilities to ensure compliance with the group A pesticides, cyanide, bis(2-ethylhexyl)phthalate, and iron effluent limitations contained in WDR Order No. R5-2007-0039.Status: Historical | |
| Sep 17, 2008 | Administrative Civil LiabilityOrder R5-2008-0571 | MMP Complaint issued in the amount of $3,000 for effluent limitation violation from 3/13/2007 to 1/31/2008. There was 1 non-serious violation.The Water Board marks this as a mandatory minimum penalty.Status: Historical | Penalty required |
| Aug 19, 2008 | Notice of Violation | Status: Historical | |
| May 4, 2007 | Time Schedule OrderOrder R5-2007-0040 | TSO issued for the discharger to develop, submit, and implement methods of compliance including pollution prevention activities, or construct necessary treatment facilities to ensure compliance with the group A pesticides, cyanide, bis(2-ethylhexyl)phthalate, and iron effluent limitations contained in WDR Order No. R5-2007-0039.Status: Historical | |
| Mar 22, 2005 | Notice of Violation | | |