| Sep 18, 2025 | Notice of Violation | Status: Historical | |
| Aug 21, 2025 | Notice of Violation | Status: Historical | |
| Jul 31, 2024 | Notice of Violation | Status: Historical | |
| Aug 24, 2023 | Notice of Violation | Status: Historical | |
| May 31, 2023 | Notice of Violation | Status: Historical | |
| Jan 11, 2023 | Oral Communication | Mike Nilsen spoke with Discharger regarding deficient monitoring and reporting at site and informed them of violations and to try to make sure all samples are taken during discharge period, especially extra sampling required at effluent and downstream receiving water monitoring location RSW-002 when discharging from the WWTP.Status: Historical | |
| Sep 29, 2022 | Notice of Violation | Status: Historical | |
| Aug 15, 2022 | Notice of Violation | Status: Historical | |
| Feb 7, 2022 | Oral Communication | Staff spoke with Discharger and verified that Discharger understands SPL samples are required per the permit.Status: Historical | |
| Feb 2, 2022 | Oral Communication | Staff spoke with Pat Guillory on 1/31/2022 regarding deficient monitoring during recent months. As noted in the violations, some samples were missed due to sampler not able to make it to site due to weather, and others were missed due to new monitoring requirements since GW wells were installed in summer.Status: Historical | |
| Dec 1, 2020 | Oral Communication | Staff spoke with Discharger about deficient monitoring for 2020 year. Main reasons for deficient monitoring are new operators and new lab collecting samples. Staff is working with Discharger and new operators/lab coordinators to verify that all samples are taken according to permit.Status: Historical | |
| Oct 27, 2020 | Administrative Civil LiabilityOrder R5-2020-0544 | ACLO with settlement of Compliance Projects 1 and 2.Status: Historical | Penalty required |
| Apr 30, 2020 | Oral Communication | Staff spoke with Discharger regarding deficient monitoring violations and referenced new permit requirements as reason for missing certain sampling frequenciesStatus: Historical | |
| Feb 5, 2020 | Time Schedule OrderOrder R5-2020-0900 | Status: Active | |
| Aug 7, 2019 | Notice of Violation | Status: Historical | |
| Aug 7, 2019 | Oral Communication | Staff spoke with Discharger about deficient monitoring, noting that operator turnover was part of issue and will soon be resolved.Status: Historical | |
| Feb 21, 2019 | Notice of Violation | Violations included in this NOV include violations that were included in NOV dated 10/4/2018. Also attached to this Amended NOV is a response to Discharger commentsStatus: Historical | |
| Dec 7, 2018 | Time Schedule OrderOrder R5-2018-0904 | Allows exceedance of Copper over the CTR effluent limitations.Status: Historical | |
| Oct 4, 2018 | Notice of Violation | Violations included in this NOV are replaced in the NOV dated 2/21/2019Status: Historical | |
| May 16, 2017 | Notice of Violation | Violations included in this NOV are replaced in the NOV dated 2/21/2019Status: Historical | |
| Apr 4, 2014 | Oral Communication | Have spoken multiple times with operator over the past couple of months. Site visit to the facility on 3/13 to train operator in proper eSMR procedures. Deficient monitoring issues have been discussed and resolved. Appropriate PET tools for the discharger have been developed and implemented.Status: Historical | |
| Dec 9, 2013 | Notice of Violation | Status: Historical | |
| Nov 5, 2012 | Oral Communication | Discussed deficient monitoring with Discharger,Status: Historical | |
| Jun 8, 2012 | Time Schedule OrderOrder R5-2012-0047 | Status: Historical | |
| May 23, 2012 | Staff Enforcement Letter | Status: Historical | |
| Aug 29, 2011 | Staff Enforcement Letter | No Spill Certification had not been entered in CIWQS since January 2011. Mr. Mark stated that he was up to date with his entries in CIWQS; I told him that the entries were not showing in CIWQSStatus: Historical | |
| Aug 10, 2011 | Oral Communication | Contacted Discharger regarding deficient monitoring.Status: Historical | |
| Jun 17, 2011 | Staff Enforcement Letter | Status: Historical | |
| Mar 18, 2011 | Administrative Civil LiabilityOrder R5-2010-0543 | Delleker submitted proof of their compliance project on November 26, 2012.Status: Historical | Penalty required |
| Jul 21, 2010 | Investigative order (Water Code 13267) | Status: Historical | |
| Jul 21, 2010 | Letter to Regulated Entity | | |
| Jul 15, 2010 | Notice of Violation | Letter detailing violations that are subject to MMPs for January through April 2010.The Water Board marks this as a mandatory minimum penalty.Status: Historical | |
| Jul 15, 2010 | Notice of Violation | NOV issued for deficient monitoring.Status: Historical | |
| Sep 14, 2009 | Notice of Violation | Status: Historical | |
| Mar 16, 2009 | Administrative Civil LiabilityOrder R5-2009-0501 | MMP Order replaces MMP Complaint for the same liability amount of $9,000. The discharger qualifies as a small community under financial hardship therefore the MMPO allows the discharger to complete a compliance project. The discharger is in the process of spending an est. $9,000 on a compliance project to purchase & install a new bisulfate analyzer & new aerator for their sewer ponds. Once completed, the discharger will have expended in excell of the mmp liability.The Water Board marks this as a mandatory minimum penalty.Status: Historical | Penalty required |
| Sep 8, 2008 | Notice of Violation | Exceedance of pH of 9Status: Historical | |
| Aug 27, 2008 | Staff Enforcement Letter | Status: Historical | |
| Jul 10, 2008 | Notice of Violation | NOV for sewer system overflow on 11 february 2008Status: Historical | |
| Jul 10, 2008 | Staff Enforcement Letter | Letter discussing effluent pH Exceedances in April 007Status: Historical | |
| Apr 4, 2008 | Notice of Violation | NOV for not having at least one pond has less than 2 feet of freeboard, which is a violation of the facilities waste discharge requirementStatus: Historical | |
| Apr 30, 2007 | Staff Enforcement Letter | Failure to report influent BOD and TSS for all four weeksStatus: Historical | |
| Nov 8, 2006 | Oral Communication | Exceedance of TSS and BOD removal limitations for Feb 06. Called Discharger on 11/08/06 to inform of violation.Status: Historical | |
| Nov 8, 2006 | Oral Communication | Exceedance of TSS removal limitations for March 06. Called discharger on 11/08/06 and relayed info re violation.Status: Historical | |
| Jun 14, 2005 | Oral Communication | Violation of effluent percent TSS and BOD removal.Status: Historical | |
| Jun 13, 2005 | Oral Communication | Violated requirement for % BOD & TSS removal, Is back in compliance.Status: Historical | |