Colfax City, a city agency, operates the site. Its industry is listed as wastewater treatment facility. It reports monitoring results to the state.

23550 Grand View Avenue, Colfax

General permit

This facility reports monitoring results to the state.

The permit's limits are not available to compare them with. The Water Board took 62 enforcement actions, 9 of which required a penalty.

Clean WaterGeneral permit

Limits not available

Clean Water Act. Source: California State Water Resources Control Board and U.S. Environmental Protection Agency, data as of November 25, 2026.

Facility type
General permit: Sewage plants that meet water quality standards at the discharge point
Discharger
Colfax City
Regional Water Board
Region 5S
Size
Minor facilityAs the EPA classes it.
Design flow
0.8 million gallons a day

What the public records hold

Monitoring results
60 parameters, latest Aug 31, 2026
Permit limits
Not available
Reported values over the permit's limit, last three years
Not available
Violations the Water Board recorded
Not available
Enforcement actions
62Has been required to pay penalties.

Permit

PermitTypeStatusEffectiveExpires
CAG585001Order R5-2023-0025Sewage plants that meet water quality standards at the discharge pointGeneral permitActiveNov 1, 2023Oct 31, 2028

What the facility reported

Results the facility reported to the state for the last three years, one row per pollutant as the permit lists them. A pollutant over its limit opens to each value over: which limit, where, and when. Each month shows the monthly average the facility reported, or the highest result that month when it filed no average.

What it discharges
ParameterLatest resultHistory
FlowEFF-0010.13 MGDAug 31, 2026
pHEFF-0017.1 SUAug 26, 2026
TemperatureEFF-00124 Degrees CAug 26, 2026
Ammonia (as N)EFF-0010.097 mg/LAug 26, 2026
Biochemical oxygen demand (BOD)EFF-001Not detectedAug 26, 2026
Total suspended solidsEFF-001Not detectedAug 26, 2026
Dissolved oxygenEFF-0015.2 mg/LAug 26, 2026
Nitrate (as N)EFF-0016.5 mg/LAug 4, 2026
Nitrite (as N)EFF-0010.32 mg/LAug 4, 2026
Electrical conductivityEFF-001423 umhos/cmAug 4, 2026
Nitrate plus nitrite (as N)EFF-0016.8 mg/LAug 4, 2026
Hardness (as CaCO3)EFF-001130 mg/LAug 10, 2026
1,1,2,2-TetrachloroethaneEFF-001Not detectedAug 27, 2025
BromomethaneEFF-001Not detectedAug 27, 2025
ChloromethaneEFF-001Not detectedAug 27, 2025
DibromochloromethaneEFF-001Not detectedAug 27, 2025
Bis(2-ethylhexyl) phthalateEFF-0013.5 ug/LAug 10, 2026
Dissolved Organic CarbonEFF-0015.3 mg/LAug 10, 2026
1,1-DichloroethaneEFF-001Not detectedAug 27, 2025
1,1-DichloroethyleneEFF-001Not detectedAug 27, 2025
1,1,1-TrichloroethaneEFF-001Not detectedAug 27, 2025
1,1,2-TrichloroethaneEFF-001Not detectedAug 27, 2025
1,2-DichlorobenzeneEFF-001Not detectedAug 27, 2025
1,2-DichloroethaneEFF-001Not detectedAug 27, 2025
1,2-DichloropropaneEFF-001Not detectedAug 27, 2025
1,2,4-TrichlorobenzeneEFF-001Not detectedAug 27, 2025
1,3-DichlorobenzeneEFF-001Not detectedAug 27, 2025
1,4-DichlorobenzeneEFF-001Not detectedAug 27, 2025
2-Chloroethylvinyl EtherEFF-001Not detectedAug 27, 2025
2-ChlorophenolEFF-001Not detectedAug 27, 2025
2,3,7,8-TCDD (Dioxin)EFF-001Not detectedAug 27, 2025
4,4'-DDDEFF-001Not detectedAug 27, 2025
4,4'-DDEEFF-001Not detectedAug 27, 2025
4,4'-DDTEFF-001Not detectedAug 27, 2025
AcroleinEFF-001Not detectedAug 27, 2025
AcrylonitrileEFF-001Not detectedAug 27, 2025
AldrinEFF-001Not detectedAug 27, 2025
Alpha-BHCEFF-001Not detectedAug 27, 2025
Alpha-ChlordaneEFF-001Not detectedAug 27, 2025
Aluminum, totalEFF-00122 ug/LAug 27, 2025
Antimony, total recoverableEFF-0010.94 ug/LAug 27, 2025
Arsenic, total recoverableEFF-0010.44 ug/LAug 27, 2025
AsbestosEFF-001Not detectedAug 27, 2025
BenzeneEFF-001Not detectedAug 27, 2025
Beryllium, total recoverableEFF-001Not detectedAug 27, 2025
Beta-BHCEFF-001Not detectedAug 27, 2025
Boron, totalEFF-001150 ug/LAug 27, 2025
BromoformEFF-001Not detectedAug 27, 2025
Cadmium, total recoverableEFF-001Not detectedAug 27, 2025
Carbon TetrachlorideEFF-001Not detectedAug 27, 2025
ChlordaneEFF-001Not detectedAug 27, 2025
ChlorobenzeneEFF-001Not detectedAug 27, 2025
ChloroethaneEFF-001Not detectedAug 27, 2025
ChloroformEFF-0010.21 ug/LAug 27, 2025
Chromium (III)EFF-0011.1 ug/LAug 27, 2025
Chromium (VI)EFF-001Not detectedAug 27, 2025
Cis-1,3-DichloropropeneEFF-001Not detectedAug 27, 2025
Copper, total recoverableEFF-0015.4 ug/LAug 27, 2025
CyanideEFF-00129 ug/LAug 27, 2025
Delta-BHCEFF-001Not detectedAug 27, 2025

Reported values over the permit's limit

Monthly reports the facility filed with the EPA, compared with the permit's limit for the same measure. A value counts only when it was detected and the limit was in force on that date.

Not available

Violations the Water Board recorded

Not available. The Water Board's violation records for this kind of facility are not published as data we can read.

Enforcement actions

Notices, orders, and penalties the Water Board issued.

DateActionDetailsPenalty
Oct 21, 2026Notice of ViolationFrom another Water Board program: Waste discharge requirementsStatus: Historical
Sep 16, 2025Administrative Civil LiabilityOrder R5-2025-0519The Parties have engaged in confidential settlement negotiations and agree to settle the matter without administrative or civil litigation by presenting this Stipulated Order to the Central Valley Water Board, or its delegee, for adoption as an order by settlement, pursuant to Water Code section 13323 and Government Code section 11415.60. To resolve the violations by consent and without further administrative proceedings, the Parties have agreed to the imposition of an ACL in the amount of th...The Water Board marks this as a mandatory minimum penalty.Status: ActivePenalty required
Feb 18, 2025Notice of ViolationStatus: Historical
Nov 26, 2024Administrative Civil LiabilityOrder R5-2024-0514The Parties have engaged in confidential settlement negotiations and agree to settle the matter without administrative or civil litigation by presenting this Stipulated Order to the Central Valley Water Board, or its delegee, for adoption as an order by settlement, pursuant to Water Code section 13323 and Government Code section 11415.60. To resolve the violations by consent and without further administrative proceedings, the Parties have agreed to the imposition of an ACL in the amount of th...The Water Board marks this as a mandatory minimum penalty.Status: HistoricalPenalty required
Sep 12, 2024Notice of ViolationStatus: Historical
Apr 8, 2024Notice of ViolationStatus: Historical
Sep 15, 2023Notice of ViolationStatus: Historical
May 5, 2023Notice of ViolationStatus: Historical
Sep 2, 2022Notice of ViolationStatus: Historical
Mar 8, 2022Notice of ViolationStatus: Historical
Jun 25, 2021Notice of ViolationStatus: Historical
Jan 22, 2020Notice of ViolationStatus: Historical
Oct 22, 2018Notice of ViolationStatus: Historical
Apr 12, 2017Notice of ViolationStatus: Historical
Mar 20, 2017Notice of ViolationStatus: Historical
Sep 28, 2016Administrative Civil LiabilityOrder R5-2016-0562The Complaint charges the Discharger with an administrative civil liability in the amount of $21,000 for effluent limitation violations that occurred between 1 January 2015 and 30 June 2016. This Complaint alleges seven total coliform violations.Status: HistoricalPenalty required
Aug 1, 2016Notice of ViolationStatus: Historical
Jul 19, 2016Notice of ViolationStatus: Historical
Apr 7, 2016Notice of ViolationStatus: Historical
Nov 3, 2015Notice of ViolationStatus: Historical
Jul 10, 2015Notice of ViolationStatus: Historical
Jun 11, 2015Administrative Civil LiabilityOrder R5-2015-0529The Order assesses administrative civil liability in the amount of $12,000, which represents the sum of the statutory Mandatory Minimum Penalties (MMPs) for effluent limit violations which occurred between 1 January 2014 and 31 December 2014. The Order suspends the $12,000 penalty upon completion of two compliance projects, which consist of constructing a permanent ultraviolet disinfection system enclosure and a mixer conversion project to reduce ammonia in the discharge.The Water Board marks this as a mandatory minimum penalty.Status: HistoricalPenalty required
Feb 25, 2015Notice of ViolationStatus: Historical
Jan 8, 2015Notice of ViolationStatus: Historical
Aug 18, 2014Notice of ViolationStatus: Historical
May 7, 2014Administrative Civil LiabilityOrder R5-2014-0531MMP Order issued in the amount of $9,000 for 3 serious effluent violations occurring between 1 June 2013 and 31 December 2013 (data reported under Monitoring and Reporting Programs R5-2007-0130 and R5-2013-0045). The Discharger shall remit payment of $4,500 by 8 June 2014. The remaining $4,500 shall be suspended, pursuant to Water Code section 13385(l), pending completion of the Supplemental Environmental Project (SEP) that the Discharger is currently required to complete under Order R5-2013-...The Water Board marks this as a mandatory minimum penalty.Status: HistoricalPenalty required
Mar 21, 2014Notice of ViolationStatus: Historical
Dec 13, 2013Notice of ViolationStatus: Historical
Oct 16, 2013Notice of ViolationStatus: Historical
Oct 1, 2013Administrative Civil LiabilityOrder R5-2013-0582MMP Order issued in the amount of $27,000 for 9 serious effluent violations occurring between 1 October 2012 and 31 March 2013 (data reported under Monitoring and Reporting Program R5-2007-0130). Discharger shall pay $6,000 to the State Board's Cleanup and Abatement Account. The remaining $21,000 shall be suspended, pursuant to Water Code section 13385(l), pending completion of a Supplemental Environmental Project (SEP). If the final cost of the successfully completed SEP is less than the sus...The Water Board marks this as a mandatory minimum penalty.Status: HistoricalPenalty required
Aug 30, 2013Notice of ViolationStatus: Historical
Jul 19, 2013Cease and Desist OrderOrder R5-2013-0046CDO requires compliance with the new effluent limitation by 30 May 2016: to retain effluent limitations for aluminum, copper, cyanide, bis (2-ethylhexyl) phthalate, electrical conductivity, iron, settleable solids, turbidity, and the mercury mass limitationStatus: Historical
Jul 12, 2013Notice of ViolationStatus: Historical
May 6, 2013Notice of ViolationDuring the monitoring periods January 2013, February 2013, March 2013, and First Quarter 2013 the discharge violated the limitations contained in the WDRs.Status: Historical
Mar 12, 2013Notice of ViolationDuring the monitoring periods December 2012, Fourth Quarter 2012, and Annual 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Feb 1, 2013Notice of ViolationDuring the monitoring period November 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Jan 7, 2013Administrative Civil LiabilityOrder R5-2013-0500MMP Order issued in the amount of $33,000 for 6 serious and 5 non-serious effluent limitation violations from 07/01/2011 to 09/30/2012. A $9,980 portion of the penalty for the effluent copper violations has been satisfied through the completion of the compliance project. The $9,000 portion of the penalty associated with the two turbidity and one bis (2-ethylhexyl) phthalate violations shall be permanently suspended if the Discharger submits evidence that it has spent at least $9,000 and compl...The Water Board marks this as a mandatory minimum penalty.Status: HistoricalPenalty required
Jan 3, 2013Notice of ViolationDuring the monitoring period October 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Nov 29, 2012Notice of ViolationDuring the monitoring period September 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Oct 16, 2012Notice of ViolationDuring the monitoring period August 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Oct 10, 2012Notice of ViolationA compliance evaluation inspection was conducted on 6 September 2012 to determine compliance with the WDRs one area was unsatisfactory.The influent composite sampler is not refrigerated and sample temperature is not controlled. WDRs Standard Provision III.B requires the Discharger to conduct sampling in accordance with 40 CFR Part 136.Status: Historical
Sep 19, 2012Notice of ViolationDuring the monitoring periods June 2012 and July 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Aug 8, 2012Notice of ViolationStatus: Historical
Jul 25, 2012Notice of ViolationDuring the monitoring period May 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Jun 20, 2012Notice of ViolationStatus: Historical
May 21, 2012Notice of ViolationDuring the monitoring periods March 2012 and First Quarter 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Apr 27, 2012Notice of ViolationDuring the monitoring period February 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Mar 26, 2012Notice of ViolationDuring the monitoring periods January 2012, February 2012, and March 2012 the discharge violated the limitations contained in the WDRs.Status: Historical
Feb 28, 2012Notice of ViolationDuring the monitoring periods December 2011, Fourth Quarter 2011, and Annual Report 2011 the discharge violated the limitations contained in the WDRs.Status: Historical
Jan 11, 2012Notice of ViolationDuring the monitoring periods September 2011, October 2011, and Third Quarter 2011 the discharge violated the limitations contained in the WDRs.Status: Historical
Dec 8, 2011Administrative Civil LiabilityOrder R5-2011-0096MMP Order issued in the amount of $165,000 for effluent limitation violations from 1/1/2008 to 6/30/2011. There were 31 serious and 24 non-serious violations. Discharger shall pay $12,000. $39K permanently suspended by completion of CP (Finding 23), $57K shall be suspended based on evidence that $57K was spent to retain services (Finding 25), and another $57K shall be deemed satisfied if discharger complies with the WER Study time schedule (Finding 27).The Water Board marks this as a mandatory minimum penalty.Status: HistoricalPenalty required
Dec 2, 2011Cease and Desist OrderOrder R5-2011-0097CDO issued to update the 2010 CDO and address all outstanding issues at WWTP. Interim effluent limit for copper, contains an interim ave dry weather flow limit, and interim mass loading effluent limits. Also, continue rehab of sewage collection system, provide temporary operational flexibility to drain storage res for lining, and re-evaluate storage res capacity to hold ww inflows, precipitation, and I/I generated during 100-yr annual precipitation event.Status: Historical
Nov 2, 2011Notice of ViolationDuring the monitoring periods First Quarter 2011, Second Quarter 2011, July 2011, and August 2011 the discharge violated the limitations contained in the WDRs.Status: Historical
Sep 1, 2011Notice of ViolationDuring the monitoring periods May 2011 and June 2011 the discharge violated the limitations contained in the WDRs.Status: Historical
Jul 14, 2010Notice of ViolationFrom January 2008 through May 2010 the discharge violated the effluent limitations contained in the WDRs.Status: Historical
Feb 2, 2010Notice of ViolationStatus: Historical
Jan 28, 2010Cease and Desist OrderOrder R5-2010-0001CDO issued for Discharger to submit a new workplan and schedule to cease all seepage discharges to surface water, and provides additional time for the Discharger to comply with Discharge Prohibition III.A.Status: Historical
Nov 19, 2008Notice of ViolationNOV issued for chlorinated wastewater discharged from the threatment plant to an unanmed tributary of Smuthers Ravine for apprx 7.5 hours. The discharger reported that the flow was approx 450 gpm and the chlorine concentration s was 5 mg/l. This would equal a discahrge of over 200,000 gals of chlorinated effluent.Status: Historical
Jun 18, 2008Administrative Civil LiabilityOrder R5-2008-0534MMP Order issued in the amount of $234,000 for 33 serious and 45 non-serious violations from 04/01/2003 to 12/31/2007. The discharger qualifies as a small community under CWC section 13385(k)(2). The entire penalty shall be suspended if the discharger complies with a compliance project.The Water Board marks this as a mandatory minimum penalty.Status: Historical
Feb 29, 2008Notice of ViolationColfax failed to submit a report related to I/I (CDO Task 1) and submitted an incomplete report related to ceasing wastewater seepage from their storage reservoir (CDO Task 2).Status: Historical
Dec 14, 2007Cease and Desist OrderOrder R5-2007-0131Compliance with this CDO exempts the Discharger from mandatory penalties for violations of effluent limitations for nitrate, in accordance with CWC section 13385(j)(3). CWC section 13385(j)(3) requires the Discharger to prepare and implement a pollution prevention plan pursuant to section 13263.3 of the California Water Code.Status: Historical
Dec 5, 2003Administrative Civil LiabilityOrder R5-2003-0167Violated WDR Order No. 95-058 for total chlorine residual, TSS, and total coliform and WDR Order No. 5-01-180 for BOD, TSS, total coliform, and total chlorine residual. 10/19/2006 Compliance deadline extension 12/14/2006. 1/24/08 Letter from EO stating we consider the Compliance Project to have been satisfied.The Water Board marks this as a mandatory minimum penalty.Status: HistoricalPenalty required

Sources: the State Water Board's permit, monitoring, and enforcement records (CIWQS) and the EPA's monthly reports and permit limits (ICIS-NPDES). The Water Board's record for this facility (CIWQS).

Location and details

The neighborhood

About 6,327 people live in the neighborhood around this site in Colfax. The state scores it above 20% of California neighborhoods for pollution burden and health vulnerability.

Least burdenedMost burdened

Source: CalEnviroScreen 5.0, census tract 6061022002. The score covers the whole neighborhood and does not measure this site's own effect.

Permits and IDs

Industry
Wastewater Treatment Facility
Operator
Colfax City
Covered by
General discharge permit

The Water Board's record for this facility (CIWQS)

Report pollution at this site

Send photos or video of what you have seen, such as smoke, runoff, or uncovered materials. We review every report.

Send a report