EarthSpotterEarthSpotter

Grubb Rincon Field

3055 West Pacific Coast Highway, Ventura, CA 93001

CalNRG Operating LLC has held an industrial stormwater permit for the site since April 2022. Its industry is listed as crude petroleum and natural gas. Its runoff was over a state benchmark in each of the last four years it sampled, most recently in 2025-26 for suspended solids. Under its stormwater permit it is at Exceedance Response Action Level 2 for suspended solids, which means it must file an action plan with the state.

3055 West Pacific Coast Highway, Ventura

Industrial stormwater

During the 2025-2026 rainy season, the site exceeded the benchmark set by the state for suspended solids.

Its yearly average for suspended solids was 4.4 times the benchmark. It has exceeded at least one benchmark in each of the last four years it sampled.

Clean WaterIndustrial stormwater

Over a state benchmark

Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.

Rain and sampling in 2025-26

The facility sampled 4 of the 12 storms of a tenth of an inch or more near the site in 2025-26.

The permit generally requires samples from four storms a year, with few exceptions.

What the samples show

The state compares each year's average with its benchmark. A site with more than one drainage area samples each one separately, so it can file more than four results for a pollutant in a year. Open a pollutant to see every lab result behind the averages.

  • Yearly average, over
  • Yearly average, within
  • Single lab result
  • State benchmark

Over the benchmark in 2025-26

Suspended solids

441 mg/L19 results, 6 drainage areas

100 mg/L

Exceedance Response Action Level 2

All results for suspended solids

Mud and fine particles that cloud water, bury habitat, and carry other pollutants.

2025-26 results by drainage area

The site samples each drainage area separately, so one storm can produce several results. The state compares the average of all of them with the benchmark.

Drainage areaResultsAverageHighest
Site A4864 mg/L3,158 mg/L
Site B3193 mg/L300 mg/L
Site C321 mg/L28 mg/L
Site D3840 mg/L1,688 mg/L
Site E3305 mg/L534 mg/L
Site F3279 mg/L438 mg/L
54 results as a table
SampledDrainage areaResult
Feb 16, 2026Site C24 mg/L
Feb 16, 2026Site B230 mg/L
Feb 16, 2026Site A158 mg/L
Nov 20, 2025Site F156 mg/L
Nov 20, 2025Site E316 mg/L
Nov 20, 2025Site D828 mg/L
Nov 20, 2025Site C28 mg/L
Nov 20, 2025Site B50 mg/L
Nov 20, 2025Site A125 mg/L
Nov 14, 2025Site F242 mg/L
Nov 14, 2025Site E66 mg/L
Nov 14, 2025Site D4.3 mg/L
Nov 14, 2025Site C11 mg/L
Nov 14, 2025Site B300 mg/L
Nov 14, 2025Site A16 mg/L
Oct 14, 2025Site F438 mg/L
Oct 14, 2025Site E534 mg/L
Oct 14, 2025Site D1,688 mg/L
Oct 14, 2025Site A3,158 mg/L
Feb 13, 2025Site D15,190 mg/L
Feb 13, 2025Site C630 mg/L
Feb 13, 2025Site B330 mg/L
Feb 13, 2025Site A62 mg/L
Feb 5, 2025Site D1,700 mg/L
Feb 5, 2025Site C38 mg/L
Feb 5, 2025Site B175 mg/L
Feb 5, 2025Site B6.9 mg/L
Feb 5, 2025Site A12 mg/L
Mar 6, 2024Site E21,080 mg/L
Mar 6, 2024Site D34,640 mg/L
Mar 6, 2024Site C404 mg/L
Mar 6, 2024Site B732 mg/L
Mar 6, 2024Site A4,820 mg/L
Dec 19, 2023Site F7,000 mg/L
Dec 19, 2023Site E670 mg/L
Dec 19, 2023Site D3,700 mg/L
Dec 19, 2023Site C195 mg/L
Dec 19, 2023Site B178 mg/L
Dec 19, 2023Site A140 mg/L
Aug 21, 2023Site E28 mg/L
Aug 21, 2023Site D120 mg/L
Aug 21, 2023Site C6 mg/L
Aug 21, 2023Site B16 mg/L
Aug 21, 2023Site A750 mg/L
Jan 14, 2023Site F3,000 mg/L
Jan 14, 2023Site E2,700 mg/L
Jan 14, 2023Site C94 mg/L
Jan 14, 2023Site B660 mg/L
Jan 14, 2023Site A3,300 mg/L
Nov 8, 2022Site F1,900 mg/L
Nov 8, 2022Site E1,200 mg/L
Nov 8, 2022Site D3,700 mg/L
Nov 8, 2022Site C1,200 mg/L
Nov 8, 2022Site B2,200 mg/L

Within the benchmark

pH

6 to 619 results, 6 drainage areas

6 to 9

All results for pH

Water that is too acidic or too alkaline harms aquatic life and makes metals more toxic.

2025-26 results by drainage area

The site samples each drainage area separately, so one storm can produce several results. The state compares the average of all of them with the benchmark.

Drainage areaResultsLowestHighest
Site A466
Site B366
Site C366
Site D366
Site E366
Site F366
54 results as a table
SampledDrainage areaResult
Feb 16, 2026Site C6
Feb 16, 2026Site B6
Feb 16, 2026Site A6
Nov 20, 2025Site F6
Nov 20, 2025Site E6
Nov 20, 2025Site D6
Nov 20, 2025Site C6
Nov 20, 2025Site B6
Nov 20, 2025Site A6
Nov 14, 2025Site F6
Nov 14, 2025Site E6
Nov 14, 2025Site D6
Nov 14, 2025Site C6
Nov 14, 2025Site B6
Nov 14, 2025Site A6
Oct 14, 2025Site F6
Oct 14, 2025Site E6
Oct 14, 2025Site D6
Oct 14, 2025Site A6
Feb 13, 2025Site D6
Feb 13, 2025Site C6
Feb 13, 2025Site B7
Feb 13, 2025Site A7
Feb 5, 2025Site D6
Feb 5, 2025Site C7.5
Feb 5, 2025Site B7
Feb 5, 2025Site B7
Feb 5, 2025Site A7
Mar 6, 2024Site E7
Mar 6, 2024Site D7
Mar 6, 2024Site C7
Mar 6, 2024Site B7
Mar 6, 2024Site A7
Dec 19, 2023Site F6
Dec 19, 2023Site E6
Dec 19, 2023Site D6
Dec 19, 2023Site C6
Dec 19, 2023Site B6
Dec 19, 2023Site A6
Aug 21, 2023Site E7
Aug 21, 2023Site D7
Aug 21, 2023Site C7
Aug 21, 2023Site B7
Aug 21, 2023Site A7
Jan 14, 2023Site F7
Jan 14, 2023Site E7
Jan 14, 2023Site C7
Jan 14, 2023Site B7
Jan 14, 2023Site A7
Nov 8, 2022Site F7
Nov 8, 2022Site E7
Nov 8, 2022Site D7
Nov 8, 2022Site C7
Nov 8, 2022Site B7

Oil and grease

2.7 mg/L19 results, 6 drainage areas

15 mg/L

All results for oil and grease

Coats plants and animals and blocks oxygen from entering the water.

2025-26 results by drainage area

The site samples each drainage area separately, so one storm can produce several results. The state compares the average of all of them with the benchmark.

Drainage areaResultsAverageHighest
Site A43.4 mg/L6.5 mg/L
Site B31.6 mg/L2.4 mg/L
Site C32.1 mg/L5.1 mg/L
Site D33.8 mg/L5.9 mg/L
Site E32.4 mg/L3.7 mg/L
Site F32.8 mg/L3.8 mg/L
54 results as a table
SampledDrainage areaResult
Feb 16, 2026Site C1.2 mg/L
Feb 16, 2026Site B1.2 mg/L
Feb 16, 2026Site A1.1 mg/L
Nov 20, 2025Site F3.8 mg/L
Nov 20, 2025Site E2.3 mg/L
Nov 20, 2025Site D5.5 mg/L
Nov 20, 2025Site C5.1 mg/L
Nov 20, 2025Site B2.4 mg/L
Nov 20, 2025Site A6.5 mg/L
Nov 14, 2025Site F1.2 mg/L
Nov 14, 2025Site E1.3 mg/L
Nov 14, 2025Site DNot detected
Nov 14, 2025Site CNot detected
Nov 14, 2025Site B1.1 mg/L
Nov 14, 2025Site A1.2 mg/L
Oct 14, 2025Site F3.5 mg/L
Oct 14, 2025Site E3.7 mg/L
Oct 14, 2025Site D5.9 mg/L
Oct 14, 2025Site A4.8 mg/L
Feb 13, 2025Site DNot detected
Feb 13, 2025Site CNot detected
Feb 13, 2025Site BNot detected
Feb 13, 2025Site ANot detected
Feb 5, 2025Site D7.7 mg/L
Feb 5, 2025Site CNot detected
Feb 5, 2025Site B1 mg/L
Feb 5, 2025Site BNot detected
Feb 5, 2025Site ANot detected
Mar 6, 2024Site E12 mg/L
Mar 6, 2024Site D4.9 mg/L
Mar 6, 2024Site CNot detected
Mar 6, 2024Site BNot detected
Mar 6, 2024Site A4.4 mg/L
Dec 19, 2023Site F1.8 mg/L
Dec 19, 2023Site E1.3 mg/L
Dec 19, 2023Site D2.8 mg/L
Dec 19, 2023Site CNot detected
Dec 19, 2023Site B1 mg/L
Dec 19, 2023Site ANot detected
Aug 21, 2023Site E0.82 mg/L
Aug 21, 2023Site DNot detected
Aug 21, 2023Site CNot detected
Aug 21, 2023Site B0.89 mg/L
Aug 21, 2023Site A1.9 mg/L
Jan 14, 2023Site F0.95 mg/L
Jan 14, 2023Site ENot detected
Jan 14, 2023Site CNot detected
Jan 14, 2023Site BNot detected
Jan 14, 2023Site ANot detected
Nov 8, 2022Site F1.9 mg/L
Nov 8, 2022Site ENot detected
Nov 8, 2022Site DNot detected
Nov 8, 2022Site CNot detected
Nov 8, 2022Site B1 mg/L

Rain and sampling by year

The permit asks each site to sample two storms between July and December and two between January and June. When a site samples fewer, its results may not represent its true runoff.

  • Day with rain
  • Day sampled
2025-26

4 of 12 storms sampledTold the state it sampled every required storm

2024-25

2 of 9 storms sampledTold the state it did not sample every required storm

2023-24

3 of 15 storms sampledTold the state it sampled every required storm

2022-23

2 of 17 storms sampledTold the state it did not sample every required storm

2021-22

0 of 1 storm sampledTold the state it did not sample every required storm

2020-21

0 of 0 storms sampledNo annual report on file

Rainfall comes from the daily records of NOAA station Ojai (USC00046399), 12 miles from the site. It is the nearest station with a full record since 2015. A storm here means a tenth of an inch or more of rain after two dry days.

Location and details

Where the runoff goes

The facility reports that rain running off it drains to Pacific Ocean & Ventura River Reach 1 & 2.

Storm drains carry this runoff to creeks and the ocean without treatment.

The neighborhood

About 3,011 people live in the neighborhood around this site in Ventura. The state scores it above 49% of California neighborhoods for pollution burden and health vulnerability.

Least burdenedMost burdened

Source: CalEnviroScreen 5.0, census tract 6111009500. The score covers the whole neighborhood and does not measure this site's own effect.

Same operator

CalNRG Operating LLC holds 8 other stormwater permits:

Permits and IDs

Industry
Crude Petroleum and Natural Gas
Operator
CalNRG Operating LLC
Covered by
Industrial stormwater permit
Stormwater permit since
April 2022
Site size
4236 acres
Paved or roofed
1% of the site
State stormwater ID
4 56I029708

The state stormwater record

Report pollution at this site

Send photos or video of what you have seen, such as smoke, runoff, or uncovered materials. We review every report.