Trinity Steel Corporation has held an industrial stormwater permit for the site since August 2020. Its industry is listed as architectural and ornamental metal work. The permit requires samples of its runoff, and the last one it filed is from February 2026. Under its stormwater permit it is at Exceedance Response Action Level 1 for nitrate and nitrite, and the site is in a watershed with a state cleanup plan for chloride and nutrients.
918 Mission Rock Rd, Santa Paula
Industrial stormwater
This site filed no samples of its runoff in the 2025-2026 reporting year, although rain records show 12 storms of a tenth of an inch or more near it.
The permit requires samples in each half of the year, July to December and January to June. The last sample it filed is from February 2026.
Clean WaterIndustrial stormwater
Missing samples
Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.
Rain and sampling in 2025-26
The facility sampled 1 of the 12 storms of a tenth of an inch or more near the site in 2025-26.
The permit generally requires samples from four storms a year, with few exceptions. The facility told the state it missed storms because not enough qualifying storms occurred.
What the samples show
The state compares each year's average with its benchmark. A site with more than one drainage area samples each one separately, so it can file more than four results for a pollutant in a year. Open a pollutant to see every lab result behind the averages.
Yearly average, over
Yearly average, within
Single lab result
State benchmark
Tested in 2025-26
Pollutant2025-26 averageBenchmarkLast five years
Nitrate and nitrite
0.37 mg/L1 result
0.68 mg/L
Over in 1 of 2 years tested
Exceedance Response Action Level 1
All results for nitrate and nitrite
Feeds algae blooms that strip oxygen from creeks and lagoons.
2 results as a table
Sampled
Drainage area
Result
Feb 16, 2026
S1
0.37 mg/L
Feb 13, 2025
S1
1 mg/L
Tested once or twice and within the benchmark: pH, suspended solids, oil and grease, zinc, iron, aluminum.
Rain and sampling by year
The permit asks each site to sample two storms between July and December and two between January and June. When a site samples fewer, its results may not represent its true runoff.
Day with rain
Day sampled
2025-26
1 of 12 storms sampledTold the state: not enough qualifying storms occurred
2024-25
1 of 9 storms sampledTold the state it did not sample every required storm
2023-24
0 of 16 storms sampledTold the state it did not sample every required storm
2022-23
0 of 19 storms sampledTold the state it did not sample every required storm
2021-22
0 of 7 storms sampledTold the state it did not sample every required storm
2020-21
0 of 5 storms sampledTold the state it did not sample every required storm
JulAugSepOctNovDecJanFebMarAprMayJun
Rainfall comes from the daily records of NOAA station Camarillo 0.6 N (US1CAVT0016), 7 miles from the site. It is the nearest station with a full record since 2015. A storm here means a tenth of an inch or more of rain after two dry days.
Location and details
Where the runoff goes
The facility reports that rain running off it drains to Santa Clara River.
The site sits in a watershed with a state cleanup plan for chloride and nutrients.
Storm drains carry this runoff to creeks and the ocean without treatment.
The neighborhood
About 1,515 people live in the neighborhood around this site in Somis. The state scores it above 54% of California neighborhoods for pollution burden and health vulnerability.
Least burdenedMost burdened