EarthSpotterEarthSpotter

Ultra Marble & Granite Inc

11140 Tuxford St, Sun Valley, CA 91352

Ultra Marble Granite Inc has held an industrial stormwater permit for the site since August 2001. Its industry is listed as cut stone and stone products. Every pollutant it tested in 2025-26 averaged within the state benchmarks. The site is in a watershed with a state cleanup plan for metals and nutrients.

11140 Tuxford St, Sun Valley

Industrial stormwater

During the 2025-2026 rainy season, every pollutant this site tested in its runoff averaged within the state's benchmarks.

That is based on 12 lab results from 2 storm days.

Clean WaterIndustrial stormwater

Within the state benchmarks

Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.

Rain and sampling in 2025-26

The facility sampled 2 of the 10 storms of a tenth of an inch or more near the site in 2025-26.

The permit generally requires samples from four storms a year, with few exceptions. This site says it qualifies for a reduced schedule.

What the samples show

The state compares each year's average with its benchmark. A site with more than one drainage area samples each one separately, so it can file more than four results for a pollutant in a year. Open a pollutant to see every lab result behind the averages.

  • Yearly average, over
  • Yearly average, within
  • Single lab result
  • State benchmark

Tested in 2025-26

Suspended solids

25 mg/L4 results, 2 drainage areas

100 mg/L

All results for suspended solids

Mud and fine particles that cloud water, bury habitat, and carry other pollutants.

2025-26 results by drainage area

The site samples each drainage area separately, so one storm can produce several results. The state compares the average of all of them with the benchmark.

Drainage areaResultsAverageHighest
DP1226 mg/L29 mg/L
DP2223 mg/L39 mg/L
36 results as a table
SampledDrainage areaResult
Feb 16, 2026DP239 mg/L
Feb 16, 2026DP124 mg/L
Dec 24, 2025DP26.9 mg/L
Dec 24, 2025DP129 mg/L
Feb 13, 2025DP26.5 mg/L
Feb 13, 2025DP172 mg/L
Feb 1, 2024DP29.2 mg/L
Feb 1, 2024DP118 mg/L
Jan 4, 2023DP224 mg/L
Jan 4, 2023DP170 mg/L
Mar 28, 2022DP229 mg/L
Mar 28, 2022DP1113 mg/L
Dec 14, 2021DP25 mg/L
Dec 14, 2021DP16.1 mg/L
Jan 29, 2021DP27.6 mg/L
Jan 29, 2021DP121 mg/L
Dec 28, 2020DP26.1 mg/L
Dec 28, 2020DP17.5 mg/L
Mar 10, 2020DP212 mg/L
Mar 10, 2020DP122 mg/L
Dec 4, 2019DP27.2 mg/L
Dec 4, 2019DP1113 mg/L
Jan 31, 2019DP217 mg/L
Jan 31, 2019DP1110 mg/L
Jan 14, 2019DP233 mg/L
Jan 14, 2019DP126 mg/L
Dec 6, 2018DP24.1 mg/L
Dec 6, 2018DP1368 mg/L
Nov 29, 2018DP221 mg/L
Nov 29, 2018DP117 mg/L
Jan 8, 2018DP1449 mg/L
Jan 9, 2017DP143 mg/L
Jan 5, 2017DP140 mg/L
Dec 22, 2016DP148 mg/L
Mar 11, 2016DP194 mg/L
Feb 18, 2016DP141 mg/L

pH

6 to 64 results, 2 drainage areas

6 to 9

All results for pH

Water that is too acidic or too alkaline harms aquatic life and makes metals more toxic.

2025-26 results by drainage area

The site samples each drainage area separately, so one storm can produce several results. The state compares the average of all of them with the benchmark.

Drainage areaResultsLowestHighest
DP1266
DP2266
36 results as a table
SampledDrainage areaResult
Feb 16, 2026DP26
Feb 16, 2026DP16
Dec 24, 2025DP26
Dec 24, 2025DP16
Feb 13, 2025DP27
Feb 13, 2025DP17
Feb 1, 2024DP27
Feb 1, 2024DP17
Jan 4, 2023DP27
Jan 4, 2023DP17
Mar 28, 2022DP27
Mar 28, 2022DP17
Dec 14, 2021DP26
Dec 14, 2021DP16
Jan 29, 2021DP27
Jan 29, 2021DP17
Dec 28, 2020DP27
Dec 28, 2020DP17
Mar 10, 2020DP26
Mar 10, 2020DP16
Dec 4, 2019DP26
Dec 4, 2019DP16
Jan 31, 2019DP27
Jan 31, 2019DP17
Jan 14, 2019DP26
Jan 14, 2019DP16
Dec 6, 2018DP26
Dec 6, 2018DP16
Nov 29, 2018DP26
Nov 29, 2018DP16
Jan 8, 2018DP17
Jan 9, 2017DP17
Jan 5, 2017DP17
Dec 22, 2016DP17
Mar 11, 2016DP17.1
Feb 18, 2016DP17.1

Oil and grease

1 mg/L4 results, 2 drainage areas

15 mg/L

All results for oil and grease

Coats plants and animals and blocks oxygen from entering the water.

2025-26 results by drainage area

The site samples each drainage area separately, so one storm can produce several results. The state compares the average of all of them with the benchmark.

Drainage areaResultsAverageHighest
DP120.75 mg/L1.5 mg/L
DP221.3 mg/L2.6 mg/L
36 results as a table
SampledDrainage areaResult
Feb 16, 2026DP22.6 mg/L
Feb 16, 2026DP11.5 mg/L
Dec 24, 2025DP2Not detected
Dec 24, 2025DP1Not detected
Feb 13, 2025DP2Not detected
Feb 13, 2025DP10.9 mg/L
Feb 1, 2024DP2Not detected
Feb 1, 2024DP1Not detected
Jan 4, 2023DP21.9 mg/L
Jan 4, 2023DP13.8 mg/L
Mar 28, 2022DP21.3 mg/L
Mar 28, 2022DP11.2 mg/L
Dec 14, 2021DP21.2 mg/L
Dec 14, 2021DP1Not detected
Jan 29, 2021DP20.9 mg/L
Jan 29, 2021DP11.5 mg/L
Dec 28, 2020DP21.1 mg/L
Dec 28, 2020DP11 mg/L
Mar 10, 2020DP2Not detected
Mar 10, 2020DP12.4 mg/L
Dec 4, 2019DP21.1 mg/L
Dec 4, 2019DP1Not detected
Jan 31, 2019DP2Not detected
Jan 31, 2019DP11.8 mg/L
Jan 14, 2019DP2Not detected
Jan 14, 2019DP10.9 mg/L
Dec 6, 2018DP2Not detected
Dec 6, 2018DP11.6 mg/L
Nov 29, 2018DP2Not detected
Nov 29, 2018DP11.4 mg/L
Jan 8, 2018DP16.9 mg/L
Jan 9, 2017DP10.9 mg/L
Jan 5, 2017DP1Not detected
Dec 22, 2016DP1Not detected
Mar 11, 2016DP12.1 mg/L
Feb 18, 2016DP1Not detected

Rain and sampling by year

The permit asks each site to sample two storms between July and December and two between January and June. This site told the state it qualifies for a reduced schedule with fewer samples. When a site samples fewer than its schedule asks, its results may not represent its true runoff.

  • Day with rain
  • Day sampled
2025-26

2 of 10 storms sampledTold the state it sampled every required storm

2024-25

1 of 6 storms sampledTold the state it did not sample every required storm

2023-24

1 of 14 storms sampledTold the state it did not sample every required storm

2022-23

1 of 18 storms sampledTold the state it did not sample every required storm

2021-22

2 of 8 storms sampledTold the state it sampled every required storm

2020-21

2 of 5 storms sampledTold the state it sampled every required storm

Rainfall comes from the daily records of NOAA station Burbank Glendale Pasadena Airport (USW00023152), 2.3 miles from the site. It is the nearest station with a full record since 2015. A storm here means a tenth of an inch or more of rain after two dry days.

Location and details

Where the runoff goes

The facility reports that rain running off it drains to Los Angeles River.

The site sits in a watershed with a state cleanup plan for metals and nutrients.

Storm drains carry this runoff to creeks and the ocean without treatment.

The neighborhood

About 2,436 people live in the neighborhood around this site in Sun Valley. The state scores it above 96% of California neighborhoods for pollution burden and health vulnerability.

Least burdenedMost burdened

Source: CalEnviroScreen 5.0, census tract 6037121102. The score covers the whole neighborhood and does not measure this site's own effect.

Permits and IDs

Industry
Cut Stone and Stone Products
Operator
Ultra Marble Granite Inc
Covered by
Industrial stormwater permit
Stormwater permit since
August 2001
Site size
1 acres
Paved or roofed
100% of the site
State stormwater ID
4 19I016705

The state stormwater record

Report pollution at this site

Send photos or video of what you have seen, such as smoke, runoff, or uncovered materials. We review every report.

Send a report