Cemex Construction Materials Pacific LLC has held an industrial stormwater permit for the site since November 1992. Its industry is listed as ready-mixed concrete. The permit requires samples of its runoff, and the last one it filed is from February 2017. Under its stormwater permit it is at Exceedance Response Action Level 1 for iron, which means a qualified professional must review its pollution controls.
808 Gilman St, Berkeley
Industrial stormwater
This site last filed a sample of its runoff in February 2017.
The permit requires testing. It has filed no results for the last three years, so there is no public record of what its runoff contains.
Clean WaterIndustrial stormwater
Missing samples
Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.
Rain and sampling in 2025-26
The facility sampled none of the 16 storms of a tenth of an inch or more near the site in 2025-26.
The permit generally requires samples from four storms a year, with few exceptions. The facility told the state it missed storms because storms did not produce a discharge, all stormwater was retained on site, and the facility was not operating or was understaffed. It also gave another reason.
What the samples show
The state compares each year's average with its benchmark. A site with more than one drainage area samples each one separately, so it can file more than four results for a pollutant in a year. Open a pollutant to see every lab result behind the averages.
Yearly average, over
Yearly average, within
Single lab result
State benchmark
Not tested in the latest year
Figures are from the last year each was tested.
PollutantAverage when last testedBenchmarkLast five years
Iron
1.1 mg/L2 results
1 mg/L
Not tested
Exceedance Response Action Level 1
All results for iron
Settles out as rust-colored sludge that smothers creek beds. The state took its iron benchmark from a 2008 EPA benchmark that the EPA has since stopped using.
2 results as a table
Sampled
Drainage area
Result
Feb 9, 2017
SW-1
1.6 mg/L
Jan 10, 2017
SW-1
0.63 mg/L
Tested once or twice and within the benchmark: pH, suspended solids, oil and grease.
Rain and sampling by year
The permit asks each site to sample two storms between July and December and two between January and June. When a site samples fewer, its results may not represent its true runoff.
Day with rain
Day sampled
2025-26
0 of 16 storms sampledTold the state: storms did not produce a discharge; all stormwater was retained on site; the facility was not operating or was understaffed; another reason
2024-25
0 of 16 storms sampledTold the state it did not sample every required storm
2023-24
0 of 24 storms sampledTold the state it did not sample every required storm
2022-23
0 of 18 storms sampledTold the state it did not sample every required storm
2021-22
0 of 11 storms sampledTold the state it did not sample every required storm
2020-21
0 of 15 storms sampledTold the state it did not sample every required storm
JulAugSepOctNovDecJanFebMarAprMayJun
Rainfall comes from the daily records of NOAA station Piedmont 1.0 SE (US1CAAL0001), 6.6 miles from the site. It is the nearest station with a full record since 2015. A storm here means a tenth of an inch or more of rain after two dry days.
Location and details
Where the runoff goes
The facility reports that rain running off it drains to San Francisco Bay.
Storm drains carry this runoff to creeks and the ocean without treatment.
The neighborhood
About 2,470 people live in the neighborhood around this site in Berkeley. The state scores it above 39% of California neighborhoods for pollution burden and health vulnerability.
Least burdenedMost burdened
Source: CalEnviroScreen 5.0, census tract 6001422000. The score covers the whole neighborhood and does not measure this site's own effect.
Same operator
Cemex Construction Materials Pacific LLC holds 44 other stormwater permits: