Taylor Morrison of CA LLC operates the site. It has filed no discharge results.
Margaret Way at Doyle Road, Dublin
Construction stormwater
This construction site has filed no discharge results.
A site samples only when a storm makes it discharge. With no results, there is nothing to compare with the permit's action levels. The Water Board has recorded no violations and taken no enforcement actions here.
Clean WaterConstruction stormwater
No discharge results
Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.
Permit
Construction stormwater permit
Risk level
Risk level 2The permit requires samples of discharges at this level.
Status in the state system
Active
Covered since
January 2025
Disturbed area
14.5 acres
Project
Residential
Drains to
Arroyo Mocho
State permit ID
2 01C405894
Days above the permit's action level
The permit's action levels are a pH between 6.5 and 8.5 and turbidity of 250 NTU, checked at each discharge point for each day of discharge.
None
All field readings (2)
Date
Discharge point
pH
Turbidity
Nov 13, 2025
Lot 67 CB
7
40 NTU
Nov 13, 2025
Lot 75 CB
7.1
60 NTU
Violations the Water Board recorded
None
Enforcement actions
None
Source: the State Water Board's stormwater system (SMARTS). Sites report pH and turbidity readings taken in the field when a storm makes them discharge.
Location and details
The neighborhood
About 12,378 people live in the neighborhood around this site in Pleasanton. The state scores it above 11% of California neighborhoods for pollution burden and health vulnerability.
Least burdenedMost burdened