Schellinger Brothers operates the site. Its recent discharge results were within the permit's action levels.
6500 Old Redwood Hwy, Windsor
Construction stormwater
This construction site's discharge results in the last 12 months were within the permit's action levels.
It filed 68 field readings for pH and turbidity in that time. The Water Board has recorded no violations and taken no enforcement actions here.
Clean WaterConstruction stormwater
Within the permit's action levels
Clean Water Act. Source: California State Water Resources Control Board, data as of November 23, 2026.
Permit
Construction stormwater permit
Risk level
Risk level 2The permit requires samples of discharges at this level.
Status in the state system
Active
Covered since
August 2025
Disturbed area
1.84 acres
Project
Residential
Drains to
Russian River
State permit ID
1 49C408233
Days above the permit's action level
The permit's action levels are a pH between 6.5 and 8.5 and turbidity of 250 NTU, checked at each discharge point for each day of discharge.
None
All field readings (35)
Date
Discharge point
pH
Turbidity
Apr 22, 2026
MH 1
8.2
8.4 NTU
Apr 22, 2026
MH 2
8.2
7.7 NTU
Apr 21, 2026
MH 1
8.2
12 NTU
Apr 21, 2026
MH 2
8.2
12 NTU
Apr 20, 2026
MH 1
8.1
9.1 NTU
Apr 20, 2026
MH 2
8
11 NTU
Apr 10, 2026
MH 1
8
19 NTU
Apr 10, 2026
MH 2
8
19 NTU
Feb 25, 2026
MH 1
8.2
22 NTU
Feb 25, 2026
MH 2
8.2
22 NTU
Feb 24, 2026
MH 1
8.1
19 NTU
Feb 24, 2026
MH 2
8.2
17 NTU
Feb 19, 2026
MH 1
8.2
24 NTU
Feb 19, 2026
MH 2
8.2
24 NTU
Feb 18, 2026
MH 1
8.1
36 NTU
Feb 18, 2026
MH 2
8.3
24 NTU
Feb 17, 2026
MH 1
8.2
40 NTU
Feb 17, 2026
MH 2
8.3
41 NTU
Feb 16, 2026
MH 1
8.1
30 NTU
Feb 16, 2026
MH 2
8.1
25 NTU
Jan 6, 2026
MH 1
8
14 NTU
Jan 6, 2026
MH 2
8
15 NTU
Jan 5, 2026
MH 1
8.2
26 NTU
Jan 5, 2026
MH 2
8.2
27 NTU
Jan 2, 2026
MH 1
8.3
21 NTU
Jan 2, 2026
MH 2
8.3
20 NTU
Dec 26, 2025
MH 1
8.1
21 NTU
Dec 26, 2025
MH 2
8.2
20 NTU
Dec 24, 2025
MH 1
8.3
28 NTU
Dec 24, 2025
MH 2
8.3
30 NTU
Dec 23, 2025
MH 1
8.3
31 NTU
Dec 23, 2025
MH 2
8.3
30 NTU
Dec 22, 2025
MH 1
8.2
34 NTU
Dec 22, 2025
MH 2
8.2
35 NTU
Nov 5, 2025
MH 1
8.3
50 NTU
Violations the Water Board recorded
None
Enforcement actions
None
Source: the State Water Board's stormwater system (SMARTS). Sites report pH and turbidity readings taken in the field when a storm makes them discharge.
Location and details
The neighborhood
About 5,074 people live in the neighborhood around this site in Santa Rosa. The state scores it above 25% of California neighborhoods for pollution burden and health vulnerability.
Least burdenedMost burdened
Source: CalEnviroScreen 5.0, census tract 6097153809. The score covers the whole neighborhood and does not measure this site's own effect.